The waste-to-energy plant near Benoa port is 26% built. It will be able to process up to 1500 tonnes of waste a day, mainly from Denpasar and the resort areas in southern Bali.

Construction began in July and is due to be completed in 2027. The contractor is the Chinese company Weiming. The Governor of Bali says the company has promised to finish building the plant in October and start trial operations in November.
The plant is expected to ease the pressure on Suwung, the island's main landfill. It will generate enough electricity for about 50 thousand homes.
In early November, Bali's governor visited a similar Weiming facility in China. He said it was clean and there was no smell at all. The company promises to make the Benoa plant even better because Bali is a resort island.
Two similar power plants may be built in eastern and western Bali. Whether to build them will be decided once the first one is up and running.